Recent Achievements
Repair / Reconstruction of Submerged Dam in Haor
Under non-development revenue budget of 2019-20 financial year, among 02 districts under the jurisdiction of Sylhet O&M Circle, BWDB, Sylhet, in submerged dam reconstruction/reconstruction/breach-closing/ alternative dam construction work implementation, around 337.841 km under Sunamganj division-1 and 290.688 km under Sunamganj division-2 in a total of 37 haors and other haor sub-projects in Sunamganj district totaling 628.529 km submerged dam reconstruction/reconstruction work is going on under the management of BWDB, including District and Upazila Administration following the Amended Kabita Policies-2017 (সংশোধিত কাবিটা নীতিমালা-২০১৭) compiled by Ministry of Water Resources, People’s Republic of Bangladesh Government.Among them, 336.641 km work under Sunamganj O&M Division-1 and 290.6 km under Sunamganj O&M Division-2 have been implemented. Breach closing/closure work of the submerged dam has been completed at 135 places (7.620 km in length) of Haor in Sunamganj district. 5.00 km. restructuring work of submerged dam has also been completed in Sylhet district.
It may be mentioned that for the repair and closure of 532.393 km long dam in 48 haors in Sunamganj, programs and activities have been undertaken through 724 PICs (Project Implementation Committees) in 11 upazilas in the financial year 2021-22.By March 10, 2022, all the PIC earth-works have been completed and construction works of 130 closures have also been completed fully.
Haor crop protection:
In Sylhet and Sunamganj district, district administration, Upazila administration, local people's representatives, and actual beneficiaries have been involved in scheme-based repairing and restructuring submerged dams in haor every year through PIC. Acquired. Haor farmers are able to harvest Boro crops at home without any hindrance and the quality of livelihood has improved tremendously.
River Protection and Dredging Work:
The Bangladesh Water Development Board has been working on riverbank protection and river excavation / re-excavation in the affected areas to increase the navigability of rivers, reduce the incidence of floods in coastal villages and reduce the risk of river erosion by removing awake submerged chars.
In continuation of this, in the financial year 2019-20, 0.248 km under Sunamganj O&M Division-1, 0.500 km under Sunamganj O&M Division-2, and 0.360 km under Sylhet O&M Division river bank protection work is done. 1.00 km river re-excavation work by dredger in Sunamganj district (Partial) and 4.00 km river re-excavation work by dredger has been implemented under Sunamganj O&M Division-1 through excavators. Besides, re-excavation work of 33.50 km canal was completed in Sunamganj district.
Until the 2nd quarter of 2021-22 financial year, 28.50 km river re-excavation and 0.150 km river bank conservation work have been implemented. 3.345 km in Sunamganj district river excavation / re-excavation and 3.00 km. (Partial) excavation work has been implemented.
In addition,
Planning and Implementation: Cabinet Division, A2I, BCC, DoICT and BASIS